It has happened to me more than once. A truck at the venue gate, the setup crew waiting, and someone with a folder asking for a document nobody knew existed. You don't fix that day with technology or more staff. You fix it with a phone call to someone who has already gone home.
That's why I want to talk about permits today. They're not the fun part of producing an event, but they're what most often leaves a client without an event.
The real problem: a permit is not a document, it's a chain
When someone in marketing or procurement asks "do we have the permit?", the answer is almost never yes or no. There are several permits, and each one depends on another:
- The license for the venue or for the use of the space.
- The authorization for the event itself, depending on the jurisdiction.
- The evacuation plan and sign-off from the fire department or civil defense.
- Medical and emergency coverage.
- Insurance, with the clauses the venue requires.
- Music licensing, public road use and street closures, if they apply.
If one of them runs late, the rest are left hanging. And the one that runs late is almost always the one nobody put on the schedule.
What goes wrong (and I've seen it)
The venue says it's licensed, but for something else. A place can be licensed for events and not for that many people, or for that type of build. A temporary structure, a grandstand or a large stage often needs its own approval. The venue's license doesn't cover them.
The insurance doesn't say what the venue requires. The certificate arrives, everything looks fine, and the venue manager rejects it because a clause is missing or a name isn't on the insured list. It's fixed with one email, but if that happens on setup day, the email takes longer than the time you have.
The evacuation plan doesn't match what was built. It gets submitted with a floor plan. Then the client changes the layout, a bar moves, a booth gets added, and an emergency exit ends up blocked. What's on paper and what's on the floor have to be the same thing. If they aren't, the inspector will see it before you do.
Nobody knows who signs what. Each agency has its own timelines and its own counters, and they change. What was valid last year may not be valid today. You have to ask again every time.
How to avoid it
1. Make the permit list on day one, not once the date is set. As soon as the venue and date are confirmed, build the full list with an owner, an agency and a deadline for each item. Let the client see it. If procurement sees it from the start, there are no surprises in the invoicing or the schedule.
2. Talk to the venue before you design. Before drawing the layout, sit down with whoever manages the place and ask what they require. Some venues have their own rules on floor loads, setup hours, mandatory suppliers and insurance. It's cheaper to find out before the floor plan than after.
3. Freeze the layout with a date. Last-minute changes are part of the job, but every change has to go back through the evacuation plan. Agree on a date after which changes only happen with a review.
4. Carry everything printed and on your phone. It sounds old-fashioned, but on event day the inspector won't wait for a PDF to load. Keep a physical folder with everything, a copy on the operations lead's phone and another on the safety lead's.
5. Have someone on site who can answer. If an inspection comes, someone from the production team needs to know every document, know where it is and be able to explain how it's met on the ground. It's not enough for the office to know.
What to ask your production company
If you're hiring, these are the questions I would ask:
- Can you send me the full list of permits and who handles each one?
- What happens if one gets delayed? What's the plan B?
- Who will be at the venue if an inspection comes?
- How do you review the evacuation plan when the layout changes?
- Have you worked with this venue and this agency before?
If the answer is vague, be wary. If they tell you "don't worry, everything is under control" without showing you a single document, be more wary.
To close
Permits are invisible. When they go well, nobody mentions them. When they fail, they're all anyone talks about. My advice is simple: treat them as one more part of the production, with an owner, a date and follow-up, and not as paperwork you sort out when you get to it.
If you're putting something together and want to review the permit list before it's too late, write to us. I'd rather get a call a week before than on setup day.
Franco Ridao, founder of SOMOS DER